Supply and install temporary structural steel within a 20 storey high rise to facilitate localised demolition:

  • 12m long truss weighing 30tonne ‘skated’ into level 5 in 5tonne sections. Props on either end of truss extended down to basement level.
  • 150 temporary UB props over 19 levels.
  • Remove all steel